APPLICATION
By brush:
On vertical surface use suitable brush with synthetic bristles.
On horizontal surface use rubber slide or push-broom.
- Apply SikaTop®-107 Seal ID into prepared substrate with consumption 1 - 1.5 kg/m2 per coat. Always apply a minimum of 2 coats.
- The first coat has to be applied on the damp substrate (pre-wetted), with consumption 1 - 1.5 kg/m2 per coat.
- After the 1st coat dry (2-6 hours), apply the 2nd coat with a crosswise direction.
- Apply min. 2 coats. Maximum waiting time between first and second coats is 48 hours.
- Use Sika reinforcement membrane when necessary at corner and detailing area.
By trowel:
- Use flat trowel to distribute SikaTop®-107 Seal ID into prepared substrate with consumption 1 - 1.5 kg/m2 per coat. Always apply a minimum of 2 coats.
- The first coat has to be applied on the damp substrate (pre-wetted).
- The second coat will be applied after the first coat started to set and can support the following coat, usually after 2-6 hours depending on climate.
- Finish off by brushing with dry sponge when setting of second coat has started.
- Maximum waiting time between first and second coats is 48 hours.
- Use Sika reinforcement membrane when necessary at corner and detailing area.
IMPORTANT NOTES :
Must use component A (liquid) and B (powder) of SikaTop®-107 Seal ID in 1 set, CANNOT be replaced one of them with other material or added with other ingredients (water, cement or sand).
Protect the applied product with screed, tile, or granit.